In re Dunkin Donuts S.P. Approval
2008 VT 139
[Filed 23-Dec-2008]
|
ENTRY ORDER |
|
2008 VT 139 |
|
|
|
} } |
APPEALED FROM: |
|
|
|
} |
|
|
|
} |
|
|
|
} |
|
|
} |
||
|
|
} |
|
|
|
|
Trial Judge: Merideth Wright |
In the above-entitled cause, the Clerk will enter:
¶ 1.
Damartin Quadros appeals
the
¶ 2.
The facts which follow
are undisputed. In 2001, Quadros applied to the
Montpelier Planning Commission to replace a building at
¶ 3. While the appeal was pending, Quadros and Cumberland Farms entered into a stipulation pursuant to which Cumberland Farms agreed to drop the appeal and Quadros agreed to conform Dunkin Donuts’ construction and operation to five stipulated conditions. Only the fifth condition is relevant to this matter. It provided that the Dunkin Donuts “shall not include a drive-up service window or drive-through service.” The stipulations were incorporated into a final court order granting approval for the site plan, which was issued on March 19, 2003.
¶ 4.
Then, in December 2006, Quadros applied to the Montpelier Development Review Board
for an amended site plan to include a drive-through window. The Board
approved the 2006 amended plan, and, again, Cumberland Farms appealed the
decision to the
¶ 5.
Cumberland Farms moved
for summary judgment, arguing that Quadros was bound
by his 2003 stipulation, and that the denial of his original 2001 application
barred him from reapplying for a drive-through window. The
¶ 6.
We review grants of
summary judgment using the same standard as the trial court, and will affirm if
there is no genuine issue of material fact and the moving party is entitled to
judgment as a matter of law. In re Jolley Assocs., 2006 VT 132, ¶ 7, 181
¶ 7.
We do not agree that Quadros was required to file a Rule 60(b) motion as a
prerequisite for submitting a site plan amendment. In so ruling, the
¶ 8.
In Carrier, we
articulated the successive-application doctrine as follows: a “zoning board or
planning commission may not entertain a second application concerning the same
property after a previous application has been denied, unless a substantial
change of conditions ha[s] occurred or other considerations materially
affecting the merits of the request have intervened between the first and
second applications.” 155
¶ 9.
The
successive-application doctrine is an attempt to balance the competing concerns
of flexibility and finality in zoning decisions.[2] On the one hand, zoning decisions
must be responsive to changing circumstances. Schubach
v. Silver, 336 A.2d 328, 333 (
¶ 10.
This balance of
flexibility and finality is incompatible with a strict application of claim preclusion, which “is intended to protect the courts
and the parties from the burden of relitigation.”
Russell v. Atkins, 165
¶ 11.
The
¶ 12.
Neither does a consent
judgment incorporating a stipulated agreement differ from a judgment entered
after full litigation such that applying the strict standards of claim
preclusion to one but not the other is justifiable. We have often
indicated that a stipulated agreement incorporated into a court order has the
same preclusive effect as a final judgment on the merits. See, e.g., Pouech v. Pouech, 2006 VT 40, ¶ 20, 180 Vt. 1, 904 A.2d 70 (“Once a
stipulation is incorporated into a final order, concerns regarding finality
require that the stipulation be susceptible to attack only on grounds
sufficient to overturn a judgment.”); Johnston v. Wilkins, 2003 VT 56, ¶
8 (“[T]he stipulated settlement has the preclusive effect of a final
judgment.”); In re Cartmell’s Estate, 120 Vt.
234, 240, 138 A.2d 592, 595 (1958) (“A judgment entered up by the court upon an
agreement of the parties is, to say the least, as conclusive upon them as if
judgment was rendered in the ordinary course of the proceeding.”).
¶ 13. Quadros was free to file a successive application with the Review Board without first seeking Rule 60(b) relief. However, proper approval would require that Quadros show that the successive application “addresses all concerns that prevented approval” of the drive-through in his prior applications. In re Armitage, 2006 VT 113, ¶ 4.
Reversed and remanded.
¶ 14.
BURGESS, J.
concurring in part, dissenting in part. In keeping with the more flexible approach to res judicata in matters before the
¶ 15.
“Rule 60(b) relief is
ordinarily unavailable to relieve one from the effects of a stipulation freely
made.” Goshy v. Morey, 149
¶ 16. The settlement here allowed the applicant to proceed with a project that might have been stalled, modified, or defeated, but for the settlement. Successive application on the same settled subject matter, in this case the drive-through window, should be foreclosed to the stipulating applicant. Otherwise, no party in opposition to a permit application would risk compromise to settle litigation, for fear the other party has its fingers crossed behind its back.
|
Dissenting: |
BY THE COURT: |
|
|
|
|
|
|
|
___________________________________ |
|
|
Brian L. Burgess, Associate Justice |
Paul L. Reiber, Chief Justice |
|
|
|
|
|
|
|
|
John A. Dooley, Associate Justice |
|
|
|
|
|
|
|
|
Denise R. Johnson, Associate Justice |
|
|
|
|
|
|
|
|
Marilyn S. Skoglund, Associate Justice |
[1] Rule 60(b) allows a court to relieve a party from a “final judgment, order, or proceeding for the following reasons: (1) mistake, inadvertence, surprise, or excusable neglect; (2) newly discovered evidence which by due diligence could not have been discovered in time to move for a new trial under Rule 59(b); (3) fraud . . . misrepresentation, or other misconduct of an adverse party; (4) the judgment is void; (5) the judgment has been satisfied, released, or discharged, or a prior judgment upon which it is based been reversed or otherwise vacated, or it is no longer equitable that the judgment should have prospective application; or (6) any other reason justifying release from the operation of the judgment.” V.R.C.P. 60(b).
[2] The concerns of “flexibility and
finality” have been treated extensively in the context of Act 250
permitting. In re Nehemiah Assocs., 168