In re Route 103 Quarry (2006-546)
2008 VT 88
[Filed 03-Jul-2008]
NOTICE: This opinion is
subject to motions for reargument under V.R.A.P. 40
as well as formal revision before publication in the Vermont Reports.
Readers are requested to notify the Reporter of Decisions, Vermont Supreme
Court,
|
2008 VT 88 |
|
Supreme Court |
|
|
(J.P. Carrara and Sons, Inc.) |
|
|
|
On Appeal from |
|
|
|
|
|
|
|
|
|
|
|
|
Stephanie J. Kaplan, East Calais, and
Phoebe Mills,
James P. W. Goss of Kenlan, Schwiebert, Facey & Goss, P.C., and Alan P. Biederman of
Biederman Law Office,
PRESENT: Dooley, Johnson, Skoglund and Burgess, JJ., and Grearson, D.J.,
Specially Assigned
¶ 1.
SKOGLUND, J. Neighbors appeal the
¶ 2.
¶ 3.
In July 2005, the District 1 Environmental Commission issued an amended
permit with conditions that were unsatisfactory to the parties.
¶ 4.
As neighbors acknowledge, because the trial court determines the
credibility of witnesses and weighs the persuasive effect of evidence, this
Court “will not disturb a trial court’s factual findings unless, taking them in
the light most favorable to the prevailing party, they are clearly
erroneous.” In re Shantee
Point, Inc., 174
¶ 5.
Neighbors first argue that the court erred in concluding that the
proposed quarry expansion complies with 10 V.S.A. § 6086(a)(9)(E),
which, in relevant part, provides that a permit for the extraction of earth
resources “will be granted” when the applicant demonstrates that “the
extraction or processing operation and the disposal of waste will not have an
unduly harmful impact upon the environment or surrounding land uses and
development.” See
¶ 6. Neighbors argued that allowing the requested permit amendment would have an undue adverse impact on their quality of life in that vibrations from the blasting would cause them stress and damage their homes. While acknowledging neighbors’ concerns over the increased amount of explosives that would be allowed under the requested permit amendment, the court concluded that Carrara’s past operation of the quarry had not been a major contributing factor to alleged damage to neighbors’ homes, and that Carrara’s continued blasting within professionally accepted limits would not have an undue adverse impact on neighbors in the future. In light of the neighbors’ ongoing concerns, however, the court imposed conditions requiring Carrara: (1) to take structural surveys of adjacent properties, including video documentation, and to maintain records of those surveys, prior to conducting any future explosive blasts; (2) to maintain extensive reports for each blast for one year and to file such reports with the district commission within sixty days of the blast; (3) to provide blast notification to all adjacent property owners; and (4) in the event Carrara intended to conduct a blast using more explosives than the maximum amount used in the past, to provide notice of at least two business days to give the district commission and neighbors an opportunity to observe the blast and employ the means to record any effects of the blast.
¶ 7. On appeal, neighbors argue that the court ignored relevant, uncontroverted, and credible evidence demonstrating that blasting at the quarry had an unduly harmful impact on their lives and properties. According to neighbors, the court ignored their testimony explaining the intensity of the blasts and the physical damage to their homes. Upon review of the record, we conclude that the court did not ignore neighbors’ testimony, which was not uncontroverted.
¶ 8.
Just as neighbors submitted testimony
speculating that past blasting had caused physical damage to their mobile
homes,
¶ 9.
Given undisputed evidence that the previously allowed and currently
requested level of blasting satisfied, by a wide margin, USBM standards, and
that compliance with such standards established a high degree of certainty that
there would be no adverse effects from the blasting, the court granted the
requested permit amendment with the stringent conditions noted above. Given
this record, we find no basis to reverse the court’s determination that
¶ 10. Neighbors contend, however, that the court wrongly assumed that blasting within USBM standards would guarantee the absence of physical damage to neighboring properties. We disagree. The conditions the court imposed argue against any such guarantee.
¶ 11. Nevertheless,
neighbors argue that the court erred by granting the amended permit request
contingent upon Carrara monitoring its blasting, and
by excluding evidence of Carrara’s previous
noncompliance with permit conditions. We find no error. Evidence at
trial indicated that since at least 1994 the quarry had operated without any
claim of a violation of its Act 250 permit. Further, as the court noted,
previous permit violations that neighbors sought to introduce were related to
¶ 12. Neighbors
also complain that the court wrongly excluded certain statements made by
adjacent property owners in prefiled testimony and
then relied upon patently incredible testimony by one of Carrarra’s
witnesses concerning the possible causes of alleged physical damage to
neighbors’ homes. The court issued a detailed order accepting and
rejecting various statements submitted in prefiled
testimony describing the vulnerable nature of neighbors’ property and the
physical damage and other adverse effects allegedly caused by the
blasting. The court also heard evidence indicating that the physical
damage to neighbors’ homes was most likely the result of time, inevitable wear
and tear, deferred maintenance, improper set-up of the mobile homes, or other
causes independent of the blasting. Neighbors would have this Court
reweigh the evidence and find in their favor, but, as noted, it was the trial
court’s prerogative to assess the credibility of witnesses and weigh the
evidence. Shantee Point, Inc.,
174
¶ 13. Finally,
with respect to Criterion 9(E), neighbors argue that the court erred by not
compelling Carrara to conduct, at Carrara’s
expense for observation by the court and the parties’ experts, a test blast
using the maximum amount of explosives that would be allowed under Carrara’s amended permit request. In support of their
request for a test blast, neighbors cited V.R.C.P. 34, which allows a party to
request entry onto the land of another party for the purpose of, inter alia,
testing the land or anything thereon that might be subject to discovery in an
action pending between the parties. In denying the motion, the court
first noted that
¶ 14. On
appeal, rather than rely on Rule 34 as it did before the trial court, neighbors
now contend that former Environmental Board Rule 20, which allowed the district
commission to conduct tests to verify information in an application, provided
the court with the authority to compel
¶ 15. A test blast in this particular case may have been helpful in resolving the issues before the court, given that the district commission had imposed limitations on the blasting after itself viewing two test blasts. Both test blasts viewed by the commission used only about half of the permitted amount of explosives for each delayed explosion, and only one of the tests used the maximum level of explosives per blast sought in the most recent permit amendment request. After noting that the maximum amount of explosives per blast created noticeably greater vibrations and that Carrara had not informed the commission beforehand that it would not be using the maximum amount of explosives allowed for each delayed explosion, the commission restricted the amount of explosives per delay to the amount used in the test blasts and the total amount of explosives per blast to the amount allowed by the then-current permit. The court ultimately rejected these restrictions.
¶ 16. Although
the court would have acted within its discretion had it compelled
¶ 17. Neighbors’
next principal argument is that the court erred in concluding that Carrara’s requested permit amendment complied with 10
V.S.A. § 6086(a)(2) and (3), which require that a development have “sufficient
water available for [its] reasonably foreseeable needs” and will “not cause an
unreasonable burden on an existing water supply, if one is to be
utilized.” According to neighbors, the court failed to make adequate
findings on whether sufficient water was available for the quarry, and the
evidence did not support the court’s findings that granting the permit
amendment would not create sediment in, or otherwise have a negative impact on,
neighboring water supplies. We conclude that the court made adequate
findings on these criteria, and that those findings are supported by sufficient
evidence. See Shantee Point, Inc.,
174
¶ 18. With respect to Criterion 2, the court concluded that the quarry requires little or no water for its future operations and that its foreseeable needs will be more than adequately met by the water available at the quarry site. Because groundwater and precipitation that enter the quarry pit must be pumped out, neighbors argue that the court should have determined whether the quarry would permanently remove water that otherwise would be available to neighboring wells. We find no merit to this argument. The evidence indicated that the quarry does not use water as part of its operations. As neighbors acknowledge and the court pointed out, Criterion 2 is considered in conjunction with Criterion 3, which specifically addresses whether a development will cause an unreasonable burden on neighboring water supplies.
¶ 19. In
examining Criterion 3, the court concluded that the credible evidence offered
at trial showed that deepening the quarry by another one hundred feet would not
have a significant impact on neighboring wells. The court found that
although deepening the quarry would cause a slight decrease in the measured
head of the water in neighboring wells, the impact would be minimal and would
not result in local water supplies failing to meet current demand. The
court further concluded that the continued monitoring required of
¶ 20. Neighbors
contend, however, that their expert’s testimony demonstrated flaws in the
methodology used by
¶ 21. Neighbors
also argue that the court should have addressed, within the context of
Criterion 3 rather than Criterion 1(B) dealing with water pollution, whether
quarry blasting caused sediment to enter the water supply of an adjacent mobile
home park owned by
¶ 22. Neighbors’
last principal argument is that the court erred in finding compliance with
Criterion 1(B), which, in relevant part, requires the applicant to demonstrate
that the proposed project will not “involve the injection of waste materials or
any harmful or toxic substances into ground water or wells.” 10 V.S.A. §
6086(a)(1)(B). Neighbors are concerned that
blasting at the quarry will cause the remaining contaminants from a 1990
gasoline spill to spread to a nearby aquifer that feeds their wells, even
though the spill is located on the other side of their property from the
quarry. While deeming these concerns understandable, the court found no
direct evidence indicating that activities at the quarry were contributing in
any way to the contamination of neighboring wells from the 1990 gasoline spill,
which no one claims was related to quarry operations. The court further
found that routine past monitoring of neighboring wells showed that
contaminants from the gasoline spill continued to dissipate, even as
¶ 23. Finally, we need not address in detail neighbors’ argument, first explicitly stated in their reply brief, that the court’s evidentiary rulings demonstrated its bias against them. Nothing in the record supports this argument.
Affirmed.
|
|
|
FOR THE COURT: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|