City of
2009 VT 59
[Filed 29-May-2009]
NOTICE: This opinion is
subject to motions for reargument under V.R.A.P. 40 as well as formal revision
before publication in the Vermont Reports. Readers are requested to
notify the Reporter of Decisions, Vermont Supreme Court,
|
2009 VT 59 |
|
Supreme Court |
|
|
|
|
|
|
On Appeal from |
|
v. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Kenneth A. Schatz, City Attorney, and Brian P. Monaghan of McNeil, Leddy & Sheahan, P.C.,
Peter H. Zamore and Debra L.
Bouffard of Sheehey Furlong & Behm P.C., Richard P. Owens, Verizon
Legal Department, Defendant-Appellant.
|
|
Sarah Hofmann, Director for Public Advocacy,
Department of Public Service.
Kenneth C. Picton, Assistant General Counsel,
Public Service Corporation,
for Amicus Curiae Green Mountain Power Corporation.
Robert F. O’Neill and Norman Williams of Gravel and Shea,
Comcast, LLC.
PRESENT: Reiber, C.J., Dooley, Johnson, Skoglund and Burgess, JJ.
¶ 1.
REIBER, C.J. The Telephone Operating Company of
¶ 2.
The pertinent facts were set out in a joint statement of stipulated
facts. The City, beginning in 2004 and 2005, undertook roadway
reconstruction projects on
¶ 3. From the beginning, the parties have disputed which of them should bear the cost of undergrounding. Accordingly, before construction began, they agreed to submit the cost-sharing question to the courts for resolution. That agreement also provides that the Vermont Agency of Transportation will pay 50% of the incremental cost of undergrounding—that is, 50% of the amount by which the cost of undergrounding exceeds the cost of aerial relocation—and that the parties dispute which of them is responsible for the remaining 50% of the incremental cost. The amount in dispute is approximately $400,000.[3] The projects have now been completed, and the utility is currently providing service via the underground facilities.
¶ 4. The City, pursuant to the agreement, sought a declaratory ruling in the Chittenden Superior Court that the utility was obligated to pay the incremental undergrounding costs. After stipulating to the facts detailed above, both parties moved for summary judgment. The utility contended that it had a statutory right to place its utility facilities along streets “as long as they don’t interfere with travel or repairs,” and that the highway relocation statutes required the City to pay the disputed incremental relocation costs. The utility further argued that the City was precluded, by a 1985 settlement agreement, from recovering the disputed costs from the utility. The City contended that the utility’s rights to maintain facilities in the City’s streets were limited by the terms of the city charter and by our holding in Vermont Gas Systems, Inc. v. City of Burlington, 153 Vt. 210, 571 A.2d 45 (1989). The trial court agreed with the City and granted summary judgment in its favor, relying principally on Vermont Gas Systems.
¶ 5.
We apply the same standard as the trial court when evaluating motions
for summary judgment. Bixler v. Bullard, 172
¶ 6. The utility first claims that the trial court erred in concluding that 30 V.S.A. § 2502 did not bar the City from requiring the utility to underground its facilities at its own expense. The utility reads the section as announcing a broad “legislative determination that the right of utilities to provide service through facilities within the public right-of-way is subordinate only to the state’s interest in facilitating public travel and highway maintenance.” Put another way, the utility contends that its right to place its facilities aboveground in the public way is not subordinate to the City’s interest in promoting economic development or aesthetic values. According to the utility, the City may order it to pay for undergrounding only if its aboveground facilities pose a danger to residents or an impediment to travel.
¶ 7. For the reasons set forth in the ensuing discussion, we conclude that the right imparted by § 2502, whatever precisely it may be, is trumped by the city charter. The statute provides, in full, as follows:
Lines of telegraph, telephone and electric wires, as well as two-way wireless telecommunications facilities, may, subject to the provisions of [19 V.S.A. § 1111], be constructed and maintained by a person or corporation upon or under a highway, in such manner as not to interfere with repairs of such highway or the public convenience in traveling upon or using the same.
30 V.S.A. § 2502 (2000).[4] The statute’s import must be
assessed in light of the city charter and ordinances, 24 V.S.A. § 2291(6), and
our holding in Vermont Gas Systems, 153
¶ 8.
The trial court concluded that Vermont Gas Systems largely
controlled the outcome of the summary judgment motion, and cited that case for
the proposition that
¶ 9.
Although the trial court’s comment concerning the City’s non-aesthetic
motivation for the projects was not supported by the stipulated facts, it does
not compel us to reverse, because the applicable city ordinance plainly
requires the utility to pay for the undergrounding, regardless of its
purpose. Any error the trial court committed by indulging in presumptions
about the City’s motivations was therefore harmless. See Progressive Ins.
Co. v. Wasoka, 2005 VT 76, ¶ 20, 178
¶ 10. The City was empowered by the municipal charter to require the utility to pay for the undergrounding. The charter allows the city
[t]o fix, demand, impose and enforce such terms, conditions and regulations for the use or occupation of any street or highway in said city by any street railroad, traction, telegraph, telephone, electric, gas, electric lighting, electric power, or other company or any person enjoying the privileges, or exercising the functions of any such company aforesaid, as shall be just and reasonable, including any sum or sums of money to be paid to said city for the use of any street or highway by any or all of said companies for the purpose . . . of therein erecting and maintaining any poles, wires or any other apparatus . . . and to prohibit the use of such street by any such company or person until such terms have been complied with.
24A V.S.A. Ch. 3, § 48(40)(A)
(charter of the City of
Cost.
In the case of any public improvement project or substantial roadway
reconstruction where the placement of utility facilities underground is to be
done for aesthetic or economic development purposes, the person initiating the
project shall be responsible for securing the difference in cost between the
placement of utility facilities above ground and their placement
underground. The affected utilities shall be responsible for the costs if
placement underground is being done in the best interest of service
delivery. When the City of
The trial court did not cite the
above-emphasized language, but we conclude that it is controlling and requires
us to affirm. See Larkin v. City of
¶ 11.
Whether the charter or a generally applicable state statute controls is
a matter of statutory construction. Town of
¶ 12.
Section 48(40)(A) is more specific to the City of
¶ 13. Section 2502 simply permits specified utilities to place their facilities “upon or under a highway, in such manner as not to interfere with repairs of such highway or the public convenience in traveling.” That is, the section gives utilities a right—which may also be limited in other ways that we need not explore today—to locate their transmission facilities either aboveground or below, provided that those facilities do not interfere with repairs or travel. The statute is silent as to whether, or under what conditions, a municipality can order preexisting facilities moved to another location that also does not interfere with repairs or travel. The statute is equally silent as to who shall bear the costs of relocation.[5] Indeed, the statute does not explicitly prohibit municipalities from charging utilities a fee for placing facilities aboveground.
¶ 14.
By contrast, the city charter, quoted above, endows the City with very
specific powers over the location of utility facilities on and under its
streets, including the power to charge “just and reasonable” sums for “the
purpose . . . of therein erecting and maintaining any poles, wires or any other
apparatus in or under the surface of said street.” Charter §
48(40). If any fees imposed under the authority of the charter are not
paid, the charter gives the City the power to “prohibit the use of such street
by any such company or person until such terms have been complied with.”
¶ 15.
Although our holding in Vermont Gas Systems, 153
¶ 16.
Nor is our holding in Rutland Cable T.V. v. City of Rutland, 122
¶ 17. Rutland Cable T.V. did not deal squarely with the question we confront today. Nor does it stand for so broad a proposition as the utility assigns to it. Rather, Rutland Cable T.V. held that a city council may not, without running afoul of § 2502, arbitrarily deny a permit to one utility for activities it has already allowed another utility to do. As the opinion makes clear, however, a municipality may “determine where and in what manner” transmission facilities may be built or maintained under § 2502. Id. That holding does not foreclose the City’s actions here.
¶ 18. The utility also premises a claim of error on the theory that 19 V.S.A. §§ 1601-06 require the City to pay for the undergrounding. The sections were enacted in 1995, see 1995, No. 60 § 25, eff. April 25, 1995, and generally govern “Utility Relocations in Connection with Certain Highway Projects.” Their purpose “is to set standards for determining when and to what extent the authority granted by section 1603 of this title may be exercised.” 19 V.S.A. § 1601. Section 1603, in turn, provides that municipalities “may pay for some or all of the cost of [utility] relocation.” Id. § 1603. Where certain eligibility criteria are met, see id. § 1605, “the differential costs over and above normal relocation cost shall be apportioned on a 50/50 basis between the agency and the municipality,” id. § 1606(b). The utility claims that the statute requires the City to pay its 50% share of the differential costs without seeking contribution from the utility. But the statute is silent as to the permissible sources of city funds. In light of the charter’s express grant of authority to the City to charge “just and reasonable” sums for “the purpose of . . . erecting and maintaining any poles, wires or any other apparatus in or under the surface” of city streets, Charter § 48(40), we do not read Chapter 16 as prohibiting the City from requiring a utility to pay the City’s statutory share of the differential costs.
¶ 19. Finally, the utility contends that even if the City had the power to order undergrounding at the utility’s expense under the charter, ordinances, and statutes, the City signed that power away in a 1985 agreement settling a dispute over excavation fees. We disagree. The trial court correctly concluded that the 1985 agreement was meant to settle one particular dispute, which apparently concerned the question of whether the City could charge the utility for the right to excavate city streets to install its facilities, and not to prevent the City from imposing any undergrounding-related costs on the utility until 2014. Rather, as the agreement’s plain language reflects, it was intended to impose on New England Telephone and its successors a fixed sum per year, in exchange for which the City would “assist the Utility in the expeditious completion of its future excavations,” and would not charge the utility any fee for the right to perform those excavations. The agreement, as the trial court concluded, does not bar the City from imposing on the utility the cost of relocating lines underground.
¶ 20. The City has the power to impose undergrounding costs on the utility under a valid ordinance enacted pursuant to the charter. The charter, which is the most specific legislative enactment governing the question, will be given effect, along with the ordinance promulgated pursuant to the charter. Our Lady of Ephesus, 2005 VT 16, ¶ 16 (where two enactments may govern the same activity, Court harmonizes them by giving effect to the more specific one according to its terms). The statutory provisions upon which the utility relies are less specific and, to the extent they can be read as conflicting with the charter, must yield to it.
Affirmed.
|
|
|
FOR THE COURT: |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
[1] When the litigation began, the real party in interest was Verizon New England, Inc.
[2] The trial court rejected the verb “to underground” as jargon, but the term is in common usage in the utility industry and imparts greater meaning in that context than the more common verb “to bury.” Thus, we use the various forms of “to underground” in this opinion.
[3] The parties “expect that they will be able to determine the actual costs in the usual course of business” and without the assistance of the courts.
[4] The statute was amended in 2007 to include “broadband facilities,” but that amendment is not pertinent here. See 2007, No. 79, § 9, effective June 9, 2007.
[5] The utility concedes that it would be required to pay for the cost of relocation to any other aboveground location, and offers no principled reason that it can be made to pay for any and all aboveground relocation, but not for any underground relocation.